Mutford's Cove Road - Water and Sewer - Phase 2
Crow Head, Newfoundland and Labrador
Federal contribution
$419,802
Federal share40%
of $1.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 25, 2021
202120222023
Built
Approved 8 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Crow Head
- Construction start
- Sep 21, 2022(actual)
- Construction end
- Jun 7, 2023(actual)
Against the original forecast
- Construction start6 months lateforecast Mar 15, 2022
- Construction end6 months lateforecast Dec 5, 2022
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 57454 in the federal list. How to read these figures.