SaskPower - Battery Energy Storage System (BESS)
Federal contribution
$13.1M
$13,114,675
Federal share50%
of $26.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 31, 2021
202220232024
Built
Approved 4 weeks before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- SaskPower
- Construction start
- Jul 4, 2022(actual)
- Construction end
- Jun 28, 2024(actual)
Also in Regina
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 57479 in the federal list. How to read these figures.