Back to projects

Nigigoonsiminikaaning Waste Water System

Nigigoonsiminikaaning First Nation, Ontario

underwayWastewaterGIS
Federal contribution
$2.2M
$2,241,315
Federal share75%

of $3.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 18, 2021
202120222023202420252026
BuiltForecast

Approved 4 weeks before the announcement.

Program
Green Infrastructure Stream
Construction start
Jul 1, 2023(actual)
Construction end
Feb 1, 2026(forecast)

Also in Nigigoonsiminikaaning First Nation

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 57533 in the federal list. How to read these figures.