WRFN New Lagoon and Septic Bed Assessment/Replacement Program

Whitefish River First Nation, Ontario

completeWastewaterGIS
Federal contribution
$2.2M
$2,219,850
Federal share75%

of $3.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 18, 2021
20212022202320242025
Built

Approved 3 weeks before the announcement.

Program
Green Infrastructure Stream
Construction start
Nov 1, 2023(actual)
Construction end
Oct 17, 2025(actual)

Against the original forecast

  • Construction end2 weeks lateforecast Sep 30, 2025

Also in Whitefish River First Nation

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 57534 in the federal list. How to read these figures.