Renovation and New Construction of Conservation Area Trail Infrastructure - Trails, Boardwalks and Pedestrian Bridges

Caledon, Ontario

underwayRecreationCCRIS
Federal contribution
$1.8M
$1,768,867
Federal share40%

of $4.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 13, 2021
today
2021202320252027
BuiltForecast

Approved 7 months before the announcement.

Program
Community, Culture & Recreation Infrastructure Stream
Construction start
Apr 12, 2021(actual)
Construction end
Mar 31, 2027(forecast)

Against the original forecast

  • Construction start3 weeks lateforecast Mar 22, 2021

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 57540 in the federal list. How to read these figures.