Rehabilitation of the Township of Armstrong (Earlton) Pool Building Facility

Armstrong, Ontario

underwayRecreationCCRIS
Federal contribution
$189,200
Federal share40%

of $473.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 6, 2021
today
2021202320252027
BuiltForecast

Approved 6 months before the announcement.

Program
Community, Culture & Recreation Infrastructure Stream
Ultimate recipient
Township of Armstrong
Construction start
Apr 30, 2021(actual)
Construction end
Mar 31, 2028(forecast)

Against the original forecast

  • Construction start2.3 years earlyforecast Sep 1, 2023