Sturgeon Lake First Nation Children's Playgrounds

Sturgeon Lake, Saskatchewan

completeRecreationCCRIS
Federal contribution
$223,951
Federal share75%

of $298.6K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 31, 2021
2022
Built

Approved 8 weeks before the announcement.

Program
Community, Culture & Recreation Infrastructure Stream
Ultimate recipient
Sturgeon Lake First Nation
Construction start
Oct 5, 2021(actual)
Construction end
May 13, 2022(actual)

Against the original forecast

  • Construction start15 months lateforecast Jun 22, 2020
  • Construction end7 months lateforecast Oct 1, 2021

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 57566 in the federal list. How to read these figures.