Replacement of Skating Rink Borders - Dupuy
Federal contribution
$86,564
Federal share33%
of $259.7K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 11, 2021
20212022
Built
Approved 5 months before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- Municipality of Dupuy
- Construction start
- Jun 30, 2022(actual)
- Construction end
- Sep 15, 2022(actual)
Against the original forecast
- Construction start4 weeks lateforecast Jun 1, 2022
- Construction end2 weeks earlyforecast Sep 30, 2022