Extension of the skateboard park
Federal contribution
$46,945
Federal share33%
of $140.8K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 9, 2021
2021
Built
Approved 4 months before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- Municipality of Saint-Didace
- Construction start
- Aug 18, 2021(actual)
- Construction end
- Sep 23, 2021(actual)
Against the original forecast
- Construction start3 months lateforecast Jun 1, 2021
- Construction end8 weeks lateforecast Jul 30, 2021
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 57616 in the federal list. How to read these figures.