Redevelopment of the Lanouette Park Modules - Dixville
Federal contribution
$39,794
Federal share33%
of $119.4K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 7, 2021
20212022
Built
Approved 5 months before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- Dixville
- Construction start
- Jun 30, 2021(actual)
- Construction end
- Jun 30, 2022(actual)
Against the original forecast
- Construction start7 weeks earlyforecast Aug 17, 2021
- Construction end4 weeks lateforecast May 31, 2022
Also in Dixville
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 57618 in the federal list. How to read these figures.