Back to projects

Drinking Water Supply route 172 Ouest and rue Bouchard

Saint-Nazaire, Quebec

completeDrinking WaterGIS
Federal contribution
$344,861
Federal share40%

of $862.2K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedDec 7, 2020
20212022
Built

Approved 6 weeks before the announcement.

Program
Green Infrastructure Stream
Construction start
Sep 7, 2021(actual)
Construction end
Aug 31, 2022(actual)

Against the original forecast

  • Construction end7 weeks lateforecast Jul 15, 2022

Also in Saint-Nazaire