Drinking Water Supply route 172 Ouest and rue Bouchard
Federal contribution
$344,861
Federal share40%
of $862.2K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedDec 7, 2020
20212022
Built
Approved 6 weeks before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Municipality of Saint-Nazaire
- Construction start
- Sep 7, 2021(actual)
- Construction end
- Aug 31, 2022(actual)
Against the original forecast
- Construction end7 weeks lateforecast Jul 15, 2022
Also in Saint-Nazaire
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 57620 in the federal list. How to read these figures.