Lennox Island First Nation Wharf Design
Lennox Island First Nation, Prince Edward Island
Federal contribution
$583,338
Federal share73%
of $800.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 17, 2021
202120222023
Built
Approved 8 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Lennox Island First Nation
- Construction start
- Nov 1, 2020(actual)
- Construction end
- Mar 1, 2023(actual)
Against the original forecast
- Construction end6 weeks lateforecast Jan 16, 2023
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 57621 in the federal list. How to read these figures.