Development of water games and a service building at Parc des Berges

Saint-Paul, Quebec

completeRecreationCCRIS
Federal contribution
$242,392
Federal share33%

of $727.2K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 9, 2021
2021202220232024
Built

Approved 4 months before the announcement.

Program
Community, Culture & Recreation Infrastructure Stream
Ultimate recipient
Municipality of Saint-Paul
Construction start
Jun 1, 2023(actual)
Construction end
Mar 31, 2024(actual)

Against the original forecast

  • Construction start11 months earlyforecast May 1, 2024
  • Construction end7 months earlyforecast Oct 25, 2024