Redevelopment of the baseball fields in Richelieu Park
Federal contribution
$61,438
Federal share33%
of $186.2K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 18, 2021
20212022
Built
Approved 7 months before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- Town of Lachute
- Construction start
- Jun 21, 2021(actual)
- Construction end
- Oct 14, 2022(actual)
Against the original forecast
- Construction start3 months earlyforecast Oct 1, 2021
- Construction end11 months earlyforecast Sep 13, 2023
Also in Lachute
- Conversion of the Lachute United Church to redeploy the services of the Jean-Marc Belzile Library$5.6M
- Water Plant Upgrade with Iron and Manganese Treatment System$1.7M
- Program for the renewal of drinking water and wastewater pipes$873.4K
- Program for the renewal of drinking water and wastewater pipes$768.3K
- Program for the renewal of drinking water and wastewater pipes$597.3K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 57632 in the federal list. How to read these figures.