Construction of a Basketball Court and Three Pickleball Courts - Mont-Laurier
Federal contribution
$131,000
Federal share33%
of $393.2K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 18, 2021
2021202220232024
BuiltForecast
Approved 5 months before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- City of Mont-Laurier
- Construction start
- May 9, 2022(forecast)
- Construction end
- May 10, 2024(forecast)
Also in Mont-Laurier