Char-Lan Recreation Centre Ice Pad Replacement

South Glengarry, Ontario

completeRecreationCCRIS
Federal contribution
$535,640
Federal share40%

of $1.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 29, 2021
202120222023
Built

Approved 3 months before the announcement.

Program
Community, Culture & Recreation Infrastructure Stream
Ultimate recipient
Township of South Glengarry
Construction start
Mar 8, 2022(actual)
Construction end
May 30, 2023(actual)

Against the original forecast

  • Construction start4 weeks earlyforecast Apr 4, 2022
  • Construction end8 months lateforecast Sep 22, 2022

Also in South Glengarry

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 57672 in the federal list. How to read these figures.