Lighthouse Festival Theatre Greenroom Quality Improvement

Port Dover [Town of], Ontario

completeRecreationCCRIS
Federal contribution
$85,404
Federal share40%

of $213.5K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 6, 2021
2022
Built

Approved 4 months before the announcement.

Program
Community, Culture & Recreation Infrastructure Stream
Ultimate recipient
Lighthouse Festival Theatre
Construction start
Jan 17, 2022(actual)
Construction end
Apr 20, 2022(actual)

Against the original forecast

  • Construction end6 weeks earlyforecast May 31, 2022