Lighting and landscaping of Robert-Latour park grounds
Federal contribution
$71,518
Federal share33%
of $214.6K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 15, 2021
202120222023202420252026
BuiltForecast
Approved 4 months before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- Chénéville
- Construction start
- Mar 31, 2025(forecast)
- Construction end
- May 30, 2026(forecast)