Back to projects

Bearskin Lake Community Beach and Pavillion

Bearskin Lake First Nation, Ontario

completeRecreationCCRIS
Federal contribution
$261,117
Federal share75%

of $348.2K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 14, 2021
2022202320242025
Built
Program
Community, Culture & Recreation Infrastructure Stream
Construction start
Sep 1, 2024(actual)
Construction end
Mar 31, 2025(actual)

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 57727 in the federal list. How to read these figures.