Back to projects

Improvement of municipal park facilities

Val-Brillant, Quebec

completeRecreationCCRIS
Federal contribution
$110,002
Federal share33%

of $330.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 31, 2021
202120222023
Built

Approved 5 months before the announcement.

Program
Community, Culture & Recreation Infrastructure Stream
Construction start
Jun 1, 2022(actual)
Construction end
Mar 31, 2023(actual)

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 57749 in the federal list. How to read these figures.