Renovation of recreation and sports facilities
Federal contribution
$49,976
Federal share33%
of $149.9K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 7, 2021
202120222023
Built
Approved 5 months before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- Municipality of Saint-Adrien
- Construction start
- Sep 6, 2022(actual)
- Construction end
- Mar 31, 2023(actual)
Against the original forecast
- Construction start4 months lateforecast May 1, 2022
- Construction end10 months lateforecast May 31, 2022
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 57755 in the federal list. How to read these figures.