Renovation of recreation and sports facilities

Saint-Adrien, Quebec

completeRecreationCCRIS
Federal contribution
$49,976
Federal share33%

of $149.9K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 7, 2021
202120222023
Built

Approved 5 months before the announcement.

Program
Community, Culture & Recreation Infrastructure Stream
Construction start
Sep 6, 2022(actual)
Construction end
Mar 31, 2023(actual)

Against the original forecast

  • Construction start4 months lateforecast May 1, 2022
  • Construction end10 months lateforecast May 31, 2022

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 57755 in the federal list. How to read these figures.