Construction of a multisport surface

Ormstown, Quebec

completeRecreationCCRIS
Federal contribution
$49,016
Federal share33%

of $147.1K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 4, 2021
Built

Approved 4 months before the announcement.

Program
Community, Culture & Recreation Infrastructure Stream
Ultimate recipient
Municipality of Ormstown
Construction start
Jul 5, 2021(actual)
Construction end
Sep 25, 2021(actual)

Against the original forecast

  • Construction end4 weeks lateforecast Aug 31, 2021