Updating the Grand Valley and District Community Centre
East Luther Grand Valley, Ontario
Federal contribution
$1.1M
$1,147,500
Federal share40%
of $2.9M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 8, 2021
202120222023202420252026
Built
Approved 4 weeks before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- Town of Grand Valley
- Construction start
- May 24, 2022(actual)
- Construction end
- Jan 30, 2026(actual)
Against the original forecast
- Construction end11 months earlyforecast Dec 31, 2026