Fort Providence/Kakisa Transmission Line - Planning & Design

Fort Providence, Northwest Territories

completeGreen EnergyAEF
Federal contribution
$2.0M
$2,015,029
Federal share75%

of $2.7M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 16, 2021
2022202320242025
Built

Approved 3 months before the announcement.

Program
Arctic Energy Fund
Ultimate recipient
NT Energy
Construction start
Apr 13, 2021(actual)
Construction end
Mar 31, 2025(actual)

Against the original forecast

  • Construction start12 months lateforecast Apr 1, 2020
  • Construction end2 months earlyforecast Jun 15, 2025

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58059 in the federal list. How to read these figures.