Repair and Expansion of the Marco-Sébastien Cyr Sports Center
Federal contribution
$1.7M
$1,667,966
Federal share33%
of $5.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 12, 2021
2021202220232024
Built
Approved 8 weeks before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- Municipality of Port-DanielGascons
- Construction start
- Feb 10, 2023(actual)
- Construction end
- Jul 18, 2024(actual)
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58097 in the federal list. How to read these figures.