Renovation of municipal sports infrastructure - Municipality of Saint-Chrysostome
Federal contribution
$49,417
Federal share33%
of $148.3K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 4, 2021
2021202220232024
Built
Approved 4 months before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- Municipality of Saint-Chrysostome
- Construction start
- May 20, 2021(actual)
- Construction end
- Dec 20, 2023(actual)
Against the original forecast
- Construction start5 months earlyforecast Nov 1, 2021
- Construction end12 months lateforecast Dec 30, 2022
Also in Saint-Chrysostome