Construction of an urban and outdoor sliding center
Federal contribution
$69,723
Federal share32%
of $218.5K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 18, 2021
20212022202320242025
Built
Approved 4 months before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- Municipality of Lac-des-Écorces
- Construction start
- Nov 8, 2022(actual)
- Construction end
- Mar 27, 2025(actual)
Against the original forecast
- Construction start9 months earlyforecast Aug 1, 2023
- Construction end5 months earlyforecast Aug 14, 2025
Also in Lac-des-Écorces
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58179 in the federal list. How to read these figures.