Rehabilitation of the North Huron Wescast Community Complex (NHWCC)
Federal contribution
$335,790
Federal share40%
of $839.5K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 8, 2021
today
2021202320252027
BuiltForecast
Approved 3 months before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- Township of North Huron
- Construction start
- Jan 4, 2022(actual)
- Construction end
- Feb 28, 2027(forecast)
Also in North Huron
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58217 in the federal list. How to read these figures.