Sand Dome - Rehabilitation Acadieville
Federal contribution
$120,042
Federal share80%
of $150.1K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 13, 2021
2021
Built
Approved 8 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Province of New Brunswick
- Construction start
- Mar 19, 2021(actual)
- Construction end
- Sep 3, 2021(actual)
Against the original forecast
- Construction start8 weeks earlyforecast May 16, 2021
- Construction end4 months earlyforecast Dec 31, 2021