Sand Dome - Rehabilitation Acadieville

Acadieville, New Brunswick

completeAdministration, Emergency and Public WorksCVRIS
Federal contribution
$120,042
Federal share80%

of $150.1K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 13, 2021
2021
Built

Approved 8 months before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
Province of New Brunswick
Construction start
Mar 19, 2021(actual)
Construction end
Sep 3, 2021(actual)

Against the original forecast

  • Construction start8 weeks earlyforecast May 16, 2021
  • Construction end4 months earlyforecast Dec 31, 2021

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58230 in the federal list. How to read these figures.