Maintenance Depot - MidLife Upgrade Woodmans Point
Woodmans Point, New Brunswick
Federal contribution
$448,672
Federal share80%
of $560.8K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 5, 2021
2021
Built
Approved 8 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Province of New Brunswick
- Construction start
- Mar 16, 2021(actual)
- Construction end
- Sep 29, 2021(actual)
Against the original forecast
- Construction start2 months earlyforecast May 17, 2021
- Construction end3 months earlyforecast Dec 31, 2021
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58236 in the federal list. How to read these figures.