Back to projects

Erickson Airport Runway Rehabilitation

Clanwilliam-Erickson, Manitoba

completeRegional And Local AirportsRNIS
Federal contribution
$850,539
Federal share36%

of $2.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 26, 2021
202120222023
Built

Approved 6 months before the announcement.

Program
Rural & Northern Infrastructure Stream
Construction start
Jul 27, 2023(actual)
Construction end
Oct 24, 2023(actual)

Against the original forecast

  • Construction start8 weeks lateforecast Jun 1, 2023
  • Construction end3 weeks lateforecast Sep 30, 2023

Also in Clanwilliam-Erickson

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58250 in the federal list. How to read these figures.