Kêts’ádan´ Ku¿`

Kluane First Nation, Yukon

underwayEducation, Training and ChildcareRNIS
Federal contribution
$10.9M
$10,875,000
Federal share50%

of $21.7M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 26, 2022
today
202320242025202620272028
BuiltForecast

Approved 3 months before the announcement.

Program
Rural & Northern Infrastructure Stream
Ultimate recipient
Kluane First Nations
Construction start
Sep 20, 2024(actual)
Construction end
Oct 31, 2027(forecast)

Against the original forecast

  • Construction start4 months lateforecast May 20, 2024

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58258 in the federal list. How to read these figures.