Fisher River Cree Nation Community Road Replacement
Federal contribution
$2.6M
$2,571,597
Federal share75%
of $3.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 26, 2021
202120222023
Built
Approved 6 months before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Fisher River Cree Nation
- Construction start
- Aug 9, 2021(actual)
- Construction end
- Jul 20, 2023(actual)
Against the original forecast
- Construction start5 months lateforecast Mar 16, 2021
- Construction end6 weeks earlyforecast Aug 31, 2023
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58309 in the federal list. How to read these figures.