Back to projects

Fisher River Cree Nation Community Road Replacement

Koostatak, Manitoba

completeHighways and RoadsRNIS
Federal contribution
$2.6M
$2,571,597
Federal share75%

of $3.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 26, 2021
202120222023
Built

Approved 6 months before the announcement.

Program
Rural & Northern Infrastructure Stream
Ultimate recipient
Fisher River Cree Nation
Construction start
Aug 9, 2021(actual)
Construction end
Jul 20, 2023(actual)

Against the original forecast

  • Construction start5 months lateforecast Mar 16, 2021
  • Construction end6 weeks earlyforecast Aug 31, 2023

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58309 in the federal list. How to read these figures.