Maintenance Depot - MidLife Upgrade Loch Lomond

Loch Lomond, New Brunswick

completeVentilationCVRIS
Federal contribution
$560,000
Federal share80%

of $700.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 13, 2021
2021
Built

Approved 8 months before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
Province of New Brunswick
Construction start
Jun 1, 2021(actual)
Construction end
Dec 10, 2021(actual)

Against the original forecast

  • Construction end3 weeks earlyforecast Dec 31, 2021

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58332 in the federal list. How to read these figures.