Pointe du Bois Renewable Energy (PREP)

Pinawa, Manitoba

underwayGreen EnergyGIS
Federal contribution
$114.2M
$114,150,000
Federal share42%

of $270.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedNov 9, 2023
today
2022202420262028
BuiltForecast

Approved 21 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Manitoba Hydro
Construction start
May 1, 2023(actual)
Construction end
Oct 31, 2027(forecast)

Also in Pinawa

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58354 in the federal list. How to read these figures.