Hamiota Truck Route Network Rehabilitation
Federal contribution
$2.5M
$2,467,121
Federal share60%
of $4.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 26, 2021
202220232024
Built
Approved 4 months before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Municipality of Hamiota
- Construction start
- May 1, 2022(actual)
- Construction end
- Oct 31, 2024(actual)
Against the original forecast
- Construction start8 months lateforecast Sep 1, 2021
Also in Hamiota
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58365 in the federal list. How to read these figures.