Back to projects

Construction of a multifunctional indoor ice rink

Sainte-Madeleine, Quebec

completeRecreationCCRIS
Federal contribution
$407,066
Federal share33%

of $1.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 4, 2021
20222023
Built

Approved 4 months before the announcement.

Program
Community, Culture & Recreation Infrastructure Stream
Ultimate recipient
Village of Sainte-Madeleine
Construction start
May 5, 2022(actual)
Construction end
Jan 31, 2023(actual)

Against the original forecast

  • Construction start5 months earlyforecast Oct 1, 2022
  • Construction end4 months earlyforecast May 28, 2023

Also in Sainte-Madeleine

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58371 in the federal list. How to read these figures.