Construction of a multifunctional indoor ice rink
Federal contribution
$407,066
Federal share33%
of $1.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 4, 2021
20222023
Built
Approved 4 months before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- Village of Sainte-Madeleine
- Construction start
- May 5, 2022(actual)
- Construction end
- Jan 31, 2023(actual)
Against the original forecast
- Construction start5 months earlyforecast Oct 1, 2022
- Construction end4 months earlyforecast May 28, 2023
Also in Sainte-Madeleine
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58371 in the federal list. How to read these figures.