Back to projects

Construction of a double tennis court

Roxton Pond, Quebec

completeRecreationCCRIS
Federal contribution
$78,487
Federal share33%

of $235.5K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 4, 2021
2021202220232024
Built

Approved 4 months before the announcement.

Program
Community, Culture & Recreation Infrastructure Stream
Ultimate recipient
Municipality of Roxton Pond
Construction start
May 5, 2021(actual)
Construction end
Nov 25, 2023(actual)

Against the original forecast

  • Construction start13 months earlyforecast Jun 1, 2022
  • Construction end7 months lateforecast Apr 21, 2023

Also in Roxton Pond

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58372 in the federal list. How to read these figures.