Minnedosa Regional Event Centre New Arena

Minnedosa, Manitoba

completeRecreationRNIS
Federal contribution
$2.0M
$2,045,559
Federal share28%

of $7.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 20, 2021
20222023
Built

Approved 4 months before the announcement.

Program
Rural & Northern Infrastructure Stream
Ultimate recipient
Town of Minnedosa
Construction start
Nov 1, 2021(actual)
Construction end
Sep 9, 2023(actual)

Against the original forecast

  • Construction start7 weeks lateforecast Sep 15, 2021
  • Construction end7 weeks earlyforecast Oct 31, 2023

Also in Minnedosa

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58391 in the federal list. How to read these figures.