Fairview Heights School Modular

Halifax, Nova Scotia

completeEducation, Training and ChildcareCVRIS
Federal contribution
$2.2M
$2,200,000
Federal share80%

of $2.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 30, 2021
Built

Approved 2 months before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
Province of Nova Scotia
Construction start
May 25, 2021(actual)
Construction end
Sep 1, 2021(actual)

Against the original forecast

  • Construction start3 months lateforecast Mar 1, 2021
  • Construction end3 months lateforecast Jun 1, 2021

Also in Halifax

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58419 in the federal list. How to read these figures.