Strathcona County Emerald Hills Leisure Centre Expansion Development

Strathcona County, Alberta

completeVentilationCVRIS
Federal contribution
$1.4M
$1,361,809
Federal share68%

of $2.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 16, 2021
2021202220232024
Built

Approved 4 weeks before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
County of Strathcona
Construction start
Apr 12, 2022(actual)
Construction end
Apr 30, 2024(actual)

Against the original forecast

  • Construction start14 months lateforecast Feb 15, 2021
  • Construction end2 months earlyforecast Jun 30, 2024