Nova Scotia Municipal Electric Utility Community Solar Gardens
Federal contribution
$9.0M
$8,960,000
Federal share32%
of $28.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 8, 2021
2022202320242025
Built
Approved 4 weeks before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Alternative Resource Energy Authority
- Construction start
- Aug 18, 2022(actual)
- Construction end
- Mar 28, 2025(actual)
Against the original forecast
- Construction start5 months lateforecast Mar 31, 2022
- Construction end8 weeks lateforecast Jan 31, 2025
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58515 in the federal list. How to read these figures.