Aboriginal Heritage Gardens

Eel River Bar First Nation, New Brunswick

completeVentilationCVRIS
Federal contribution
$709,918
Federal share100%

of $709.9K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 13, 2021
202220232024
Built

Approved 6 months before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
Eel River Bar First Nation
Construction start
Jun 21, 2021(actual)
Construction end
Jan 5, 2024(actual)

Against the original forecast

  • Construction start4 months lateforecast Feb 15, 2021
  • Construction end4 weeks earlyforecast Jan 31, 2024