Renovate to reconfigure space

Casselman, Ontario

completeEducation, Training and ChildcareCVRIS
Federal contribution
$32,000
Federal share80%

of $40.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 14, 2021
20222023
Built

Approved 8 weeks before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Sep 1, 2022(actual)
Construction end
Aug 31, 2023(actual)

Against the original forecast

  • Construction start6 months lateforecast Mar 1, 2022
  • Construction end4 months earlyforecast Dec 31, 2023