Replace Existing drinking fountains with bottle filling stations; Retrofitting Open Concept Areas
Federal contribution
$328,000
Federal share80%
of $410.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 14, 2021
Built
Approved 8 weeks before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Lakehead District School Board
- Construction start
- Mar 1, 2021(actual)
- Construction end
- Sep 1, 2021(actual)
Against the original forecast
- Construction end16 months earlyforecast Dec 31, 2022
Also in Thunder Bay
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58562 in the federal list. How to read these figures.