HVAC Upgrades; Water Filling Station; Hands Free Bathroom Fixtures

Huron East, Ontario

completeVentilationCVRIS
Federal contribution
$821,600
Federal share80%

of $1.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 14, 2021
2022
Built

Approved 8 weeks before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Jul 1, 2021(actual)
Construction end
Dec 31, 2021(actual)

Against the original forecast

  • Construction start4 months lateforecast Feb 18, 2021

Also in Huron East

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58591 in the federal list. How to read these figures.