Water bottle filling stations; Handwashing Station; New Boiler/heating system

Thunder Bay, Ontario

completeVentilationCVRIS
Federal contribution
$586,808
Federal share80%

of $733.5K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 14, 2021
2022
Built

Approved 8 weeks before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Jun 15, 2021(actual)
Construction end
Dec 31, 2021(actual)

Against the original forecast

  • Construction start4 months lateforecast Feb 19, 2021
  • Construction end2 years earlyforecast Dec 31, 2023

Also in Thunder Bay

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58657 in the federal list. How to read these figures.