Installing mechanical ventilation in buildings where none currently exist; Window repair or replacement for fresh air intake
Federal contribution
$7.9M
$7,864,000
Federal share80%
of $9.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 14, 2021
202220232024
Built
Approved 8 weeks before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Waterloo Region District School Board
- Construction start
- Apr 1, 2021(actual)
- Construction end
- Dec 31, 2023(actual)
Against the original forecast
- Construction start6 weeks lateforecast Feb 18, 2021
Also in Kitchener
- Stormwater Network Adaptation$50.0M
- Aquatic Centre RBJ Schlegel Park$9.8M
- HVAC Upgrades; Upgrading wireless access points; Window replacement; Washroom upgrades; Installing cooling / air conditioning units; room partition replacement$7.6M
- Kitchener Public Library Southwest Community Library$6.0M
- Installing mechanical ventilation in buildings where none currently exist$4.9M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58679 in the federal list. How to read these figures.