New Puvirnituq Diesel Power Plant
Federal contribution
$31.0M
$30,998,250
Federal share31%
of $100.7M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 19, 2025
today
202220232024202520262027
BuiltForecast
Approved 3.3 years before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Hydro-Québec
- Construction start
- Jul 11, 2023(actual)
- Construction end
- Jan 31, 2027(forecast)
Against the original forecast
- Construction start6 weeks lateforecast Jun 1, 2023
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58731 in the federal list. How to read these figures.