New Puvirnituq Diesel Power Plant

Puvirnituq, Quebec

underwayGreen EnergyRNIS
Federal contribution
$31.0M
$30,998,250
Federal share31%

of $100.7M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 19, 2025
today
202220232024202520262027
BuiltForecast

Approved 3.3 years before the announcement.

Program
Rural & Northern Infrastructure Stream
Ultimate recipient
Hydro-Québec
Construction start
Jul 11, 2023(actual)
Construction end
Jan 31, 2027(forecast)

Against the original forecast

  • Construction start6 weeks lateforecast Jun 1, 2023

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58731 in the federal list. How to read these figures.