Back to projects

IWK Hospital - Retrofits, Repairs and Upgrades

Halifax, Nova Scotia

completeVentilationCVRIS
Federal contribution
$1.4M
$1,418,400
Federal share74%

of $1.9M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 17, 2021
2021202220232024
Built

Approved 4 weeks before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
Province of Nova Scotia
Construction start
Jun 16, 2021(actual)
Construction end
Mar 31, 2024(actual)

Against the original forecast

  • Construction start7 weeks earlyforecast Aug 1, 2021
  • Construction end6 months earlyforecast Sep 30, 2024

Also in Halifax